[JRAGANTT-396] Reset the state of issues after the deletion of dependency Created: 30/May/16  Updated: 30/May/16  Resolved: 30/May/16

Status: Resolved
Project: Gantt Chart Project for JIRA
Component/s: None
Affects Version/s: None
Fix Version/s: 3.6.21

Type: Bug Priority: Blocker
Reporter: {} Assignee: Yves YANG
Resolution: Fixed Votes: 0
Labels: None
Remaining Estimate: 1 day
Time Spent: Not Specified
Original Estimate: 1 day


 Description   
When an auto-scheduled issue depends on a resolved issue, it becomes a fixed-scheduled issue sicen its start time cannot be changed. It is normal. However, when we delete this dependency, the issue should go back to auto-scheduled.

The steps to reproduce
1. Create Task1
2. Create Task2
3. Create a dependency FS from Task1 to Task2
4. Set the Task1 to Done
5. Delete the dependency


 